Work continues at the new Attleboro High School for Arden Engineering Constructors, Earthwise Energy Technologies, and Unique Metal Works. Significant progress has been made on the four floors of the building’s north side. Equipment has been rigged to the rooftop and being connected to ductwork within the building. Arden is also starting to work on the south side mechanical rooms. Full piping systems for chilled and hot water have been fabricated. Chillers and boilers will be piped off, and hundreds of smaller individual units will be installed throughout the project. Earthwise has completed the installation of wiring controls on the north side of the building and continues on the south side.